Dual Candlestick Flare for RNG Facility Expansion

Custom-engineered dual candlestick flare system designed to meet expanded gas volumes and EPA compliance requirements at one of the largest RNG facilities in the U.S. Tell us more about your project

Project Highlights

  • 12,000 SCFM Flare Capacity
  • Custom Dual Candlestick Flare Design
  • NFPA 86 Safety Compliance
  • Real-Time Pilot Verification
  • EPA-Compliant Data Logging
  • Remote Monitoring & Control
  • Continuous & Intermittent Pilot Options
  • Annual Preventive Maintenance Program

Have Similar Equipment?

Tell us about your next project

Get a Free Quote

The Problem

The Archaea, a BP-Subsidiary, Assai RNG facility in Scranton, PA, faced a critical challenge during its multi-phase expansion. Its existing flare system could not support increased gas volumes, creating compliance risks under stringent EPA regulations.

The plant required a flare solution capable of safely combusting off-spec gas diverted from the pipeline, ensuring environmental compliance and operational continuity. With daily fines looming and critical requirements for production uptime, the customer needed a rapid, reliable, scalable solution.

Sound Familiar? Let's Talk

Before Profire

The photo depicts two flare systems at a RNG landfill location. One on the right is taller and is a dual candlestick flare. The left is a shorter flare emitting a flame. In the foreground there are two trucks, one black and one white with Profire decals on it.

The Profire Solution

After analyzing the site’s gas composition and operational needs, Profire engineered a custom dual candlestick flare system tailored to the plant’s specifications. Key elements included:

  • Dual Candlestick Flare Package – Designed for 12,000 SCFM capacity and ~78 ft height, with heat radiation modeling to ensure ground-level safety.
  • Safety-Rated Control System – Remote operation capability, redundant valve control, and NFPA 86 compliance.
  • Dual PF2100F Controllers – Provides real-time pilot verification and continuous data logging for EPA compliance.
  • Flexible Ignition Options – Continuous or intermittent pilot with auto/on-demand ignition.
  • Custom Valve Train & Piping Skid – 10-inch valve train integrated with detonation arrestor for explosion prevention.

This solution not only met compliance requirements, but also delivered operational advantages:

  • Supporting emergency gas diversion without plant shutdown.
  • Enhancing safety through remote monitoring and reduced on-site exposure.
  • Providing robust documentation and data logging for regulatory audits.

The Results

Since its commissioning in December 2022, the dual candlestick flare system has remained fully operational, successfully managing the plant’s expanded 12,000 SCFM capacity.

By integrating a safety-rated control system and pilot control, the solution has ensured continuous EPA compliance, while enabling emergency gas diversion without costly plant shutdowns. The custom valve train and remote monitoring capabilities have significantly mitigated compliance risks and enhanced operational safety through robust data logging for audits.

Profire continues to provide annual preventive maintenance, ensuring the long-term reliability and efficiency of this critical infrastructure.

 

Get a Free Quote

After Profire

The picture shows a concrete pad with a BMS controller system sitting atop. There are two controllers linked by a central communications unit. There's a mechanical box to the left of the controllers which sit in the middle of the image. Above there's a tin roof providing cover for these systems. Behind is a field with hills and a blue sky.
A dual candlestick flare piping and fuel train extends on the right of the image up the middle. The sky around the flare is grey and cloudy.
A closeup of a dual candlestick flare showing the two pilot systems as the flare extends from the bottom left of the image to the top.

Ready to Optimize your Equipment?

Let Profire help with your Safety, Reliability, and ESG Initiatives

Get a Free Quote

Recent Projects

Dual Candlestick Flare… Landfill
Details

The Archaea, a BP-Subsidiary, Assai RNG facility in Scranton, PA, faced a critical challenge during its…

See Details
Spray Dryer… Food & Beverage
Details

The customer specializes in ambient-temperature drying processes that convert juice extracts into shelf-stable powders, while preserving…

See Details
TEG Reboiler… Oil & Gas – Midstream
Details

One of our long-term customers faced the serious risk of regulatory penalties at the local, state,…

See Details